Posted on: July 3, 2018

ROAD RESURFACING IN PLANT CITY

The City of Plant City has contracted with Preferred Materials to pave 32 streets in the City.  The project is scheduled to be complete in September of 2018. In some cases only certain segments of streets will be paved.


Rain delays have altered the previous schedule.


Starting the week of August 20, 2018 paving is expected to begin on the following streets:

- S Howard St
- Sammonds Rd
- Sydney Rd
- Griffin Blvd
- Woodrow Wilson St

As the resurfacing work progresses, completed streets will be removed from this list and the work schedule will be updated until all 32 streets are completed.


For general questions contact:

Terry Ritter, Assistant City Engineer, Plant City - 813-659-4239

 

For detailed questions while work is ongoing:

Jered Lanier, Engineering Inspector, Plant City - 813-707-2341


Streets completed except for permanent striping:

  • Amberjack Blvd.                  
  • NW Drane St            
  • Chipman St
  • E Cherry St              
  • W Granfield A          
  • N Walker St
  • N Pearl St                 
  • Wheeler St                           
  • N Daniels St
  • N Thomas St
  • N Davis St                                 
  • W Herring St
  • Sansone Blvd                      
  • N Daniels St             
  • W Risk St
  • E Alabama St                       
  • W Damon St            
  • Sioux St
  • Hitchcock St             
  • N Franklin St                       
  • W Mclendon St
  • Goldfinch Dr
  • National Guard Dr                               
  • Carey St
  • Hunter St
  • N Howard St



*NOTE:

CapturePlease click on the slide button to show map legend:    